01
|
Construction of SR 304/I-269 from Station 625+00 to Station 835+00, known as Federal Aid Project Nos. STP-0029-02(016) / 102556313 & STP-0029-03(008) / 102556314 in Desoto & Marshall Counties.
Project Completion: 06/18/2015
|
|
|
|
|
|
|
|
|
|
|
02
|
Mill & Overlay approximately 7 miles of I-20 from Rankin County Line to East End of Strong River Bridges, known as Federal Aid Project No. IM-0020-02(084) / 105057301 in Scott County.
Project Completion: 06/28/2013
|
|
|
1 2 Fax1 Fax2 Fax3 QandA
|
1 2
|
|
|
|
|
|
|
03
|
Mill and Overlay approximately 10 miles of I-55 Northbound Lanes from the Copiah County Line to Byram, known as Federal Aid Project No. IM-0055-02(234) / 106476301 in Hinds County.
Project Completion: 11/16/2012
|
|
|
Fax1 QandA
|
|
|
|
|
|
|
|
04
|
Intersection Improvements (J-Turn) on US 45 at CR 212, known as Federal Aid Project No. HSIP-0002-02(063) / 106233301 in Clarke County.
Project Completion: 05/17/2013
|
|
|
Fax1 QandA
|
|
|
|
|
|
|
|
05
|
Installation of Raised Median on US 49 from Campbell Loop Road/Convention Center Ave. to 31st Ave., known as Federal Aid Project No. HSIP-0008-01(127) / 106215301 in Forrest County.
Project Completion: 04/26/2013
|
|
|
Fax1 QandA
|
|
|
|
|
|
|
|
06
|
Reconstruction of I-20 West Bound On-Ramp at Lost Gap, known as Federal Aid Project No. HSIP-0020-02(075) / 104909301, in Lauderdale County.
Project Completion: 09/13/2013
|
|
|
1 2 Fax1 QandA
|
1 2
|
|
|
|
|
|
|
07
|
POSTPONED UNTIL SEPTEMBER 25, 2012 LETTING - Grade, Drain, Bridge & Incidental Paving approximately 6 miles on SR 25 South of Becker to Existing US 278, known as Federal Aid Project No. HSIP-0040-01(021) / 101635301 in Monroe County.
Project Completion: 05/11/2015
|
|
|
Fax1 QandA
|
|
|
|
|
|
|
|
08
|
Interchange Modifications on I-59 at 16th Avenue in Laurel, known as Federal Aid Project No. HSIP-0059-02(020) / 105735301 in Jones County.
Project Completion: 07/08/2013
|
|
|
1 Fax1 QandA
|
1
|
|
|
|
|
|
|
09
|
Mill and Overlay approximately 11 miles of US 80 from the 4-lane to Lauderdale County Line, known as Federal Aid Project No. STP-0472-00(011) / 106374301 in Newton County.
Project Completion: 04/30/2013
|
|
|
Fax1
|
|
|
|
|
|
|
|
10
|
Bridge repair on US Highway 82/45 east of Columbus, known as State Project No. MRP-1082-44(021) / 304430301 in Lowndes County.
Project Completion: 11/16/2012
|
|
|
Fax1 Fax2 QandA
|
|
|
|
|
|
|
|
11
|
Mill and Overlay approximately 3 miles of US 11 from Dunns Falls Road to Arundel Road, known as State Project No. MP-5011-38(007) / 303919301 in Lauderdale County.
Project Completion: 11/20/2012
|
|
|
Fax1 QandA
|
|
|
|
|
|
|
|
12
|
Mill and Overlay approximately 3 miles of SR 16 from US 51 to end of 3-Lane in Canton, known as State Project No. MP-5016-45(011) / 304416301 in Madison County.
Project Completion: 11/15/2012
|
|
|
1 Fax1 QandA
|
1
|
|
|
|
|
|
|